HomeProofCheck a project

After purchase · Explainer

Off-plan project delayed in Dubai: what to do first

Off-plan project delayed in Dubai? What to do first: check the official record, read your SPA extension clause and keep paying only into escrow.

By HomeProof Research TeamUpdated 7 min readDubai law · every fact with a source

Short answer

  • Dubai law does not set automatic compensation for late handover; anything owed depends on your SPA and, if disputed, on a court or arbitrator.
  • The Dubai Land Department's Dubai REST app (Project Status, also called Mashrooi) shows a registered project's status, completion percentage and projected completion date.
  • Many SPAs let the developer extend the completion date, often by up to 12 months, so the extension clause decides whether the date has really been missed.
  • Stopping payments on your own can open the termination route in Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, where up to 25% or 40% of the unit value can be kept.
  • Keep every receipt and email, and pay only into the project's escrow account.

Your off-plan project is delayed in Dubai, and what to do next is the question keeping you up. The short answer: confirm the official record first, read your contract second, and only then decide whether to push, wait or escalate.

This guide covers Dubai only; each emirate has its own property regulator and rules.

Off-plan project delayed in Dubai: what to do first?

Check the government record before you call the sales team. The Dubai Land Department (DLD) publishes a status, a completion percentage and a projected completion date for every registered project, and that record is the neutral baseline for every later conversation.

  1. Open the project record

    In the DLD's Dubai REST app, go to Services and choose Project Status (Mashrooi), then search by project name. The service shows project and developer details, escrow account details and inspection details.
  2. Write down four facts

    Record the start date, projected completion date, completion percentage and last inspection date.
  3. Find the completion clause in your SPA

    Your Sale and Purchase Agreement (SPA) is the signed contract with the developer. Locate its anticipated completion date, the extension wording and the force-majeure clause.
  4. Put the gap in writing

    If the registry date is later than the SPA date, email the developer a short, dated question asking for the reason and the revised timetable.

Escrow is the dedicated account, opened in the project's name under Dubai Law No. 8 of 2007, that receives off-plan buyers' payments. Oqood is the DLD's interim register for off-plan sales.

Where can you see a Dubai off plan delay in official data?

The DLD's own systems are the place to see a delay, not the brochure. RERA, the DLD's regulatory arm, periodically reviews registered projects and asks developers to update their expected completion date and completion rate, according to the DLD's FAQ.

The DLD website also lets you check completion percentage and status by plot number, project number or project name.

Status labels in Dubai REST
active / finished / cancelled
Source: Gulf News, 2023
Independent completion report
AED 15,000
per unit or villa, from RERA's technical auditor
Source: DLD FAQ
Common SPA extension
often up to 12 months
contract term, not law
Source: Afridi & Angell
Projects stuck at 5% or less
RERA monitoring
time to correct, then cancellation steps
Source: DLD FAQ

See also how to check a changed handover date and checking construction progress before a payment.

Is an off plan handover delayed past the SPA date a breach?

Not automatically. Many SPAs give the developer a contractual right to extend the anticipated completion date, often by 12 months, and some contracts set 6 to 12 months, according to the law firms Afridi & Angell and BSA.

HAS Law Firm (July 2026) puts it plainly: "Not every delay automatically entitles a buyer to terminate the contract." Courts weigh the completion date and the reasons for the delay, force majeure, actual progress on site, and how the developer has behaved.

Read the clause for which date is the contractual one, how long the extension runs, what counts as force majeure, and whether any payment for late delivery is named.

Should you stop paying when construction is delayed by a Dubai developer?

Withholding installments without legal advice carries real risk. If a buyer defaults, Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, lets the developer start a termination process through the DLD, regardless of whether the buyer feels the delay justified it.

…stop paying the installment because the developer has stopped building?
a buyer who had paid 60 per cent, writing to Gulf News' Ask the Law · Gulf News, Oct 2023

A safer lever exists. The DLD's FAQ says that before paying a developer's request, you can ask for a letter from the DLD-approved project consultant confirming the current completion percentage. Your SPA still sets the schedule, so treat the letter as evidence.

The full tier rules are in our guide to the 25% and 40% termination tiers.

What records should you keep while the project is late?

Keep everything that shows what was promised, what you paid and when you asked. A complete file makes any later conversation with the DLD, a lawyer or a court faster.

Your delay file

When does a delay become a dispute?

A delay becomes a dispute when the written answers stop matching the record. Dubai offers two routes: DLD conciliation, which aims at an agreed settlement, and the courts or arbitration, which decide claims.

The DLD may try to settle developer and buyer disagreements, and a settlement it approves is binding under Executive Council Resolution No. 6 of 2010 (ECR 6/2010), Article 14, as summarized by Khaleej Times. The DLD cannot cancel a contract at a buyer's request; for termination, its FAQ points buyers to the real estate court.

A buyer may apply to court to terminate under ECR 6/2010, Article 20, and RERA can cancel a project for serious delay under Article 23, according to Afridi & Angell.

Whether money is owed is a separate question, covered in compensation for delayed handover. Before writing to the developer or a lawyer, pull the project's registry facts so your dates match the official record.

What should you avoid while you wait?

Avoid moves that are hard to undo, especially in the first anxious weeks.

  • Paying any amount to an account other than the project escrow account shown in Dubai REST
  • Signing an addendum that moves the completion date before reading it against your SPA
  • Relying on phone promises that nobody confirms by email
  • Stopping installments without written legal advice

Checking takes minutes; not checking can cost everything.

Buying from the UK, US, Canada or Australia?

Is a Dubai off plan delay grounds for a refund?
A Dubai off-plan delay is not, by itself, grounds for a refund. Many SPAs allow the developer to extend the completion date, often by up to 12 months. A buyer can apply to court to terminate, but courts weigh the reasons for the delay, force majeure, actual progress and the developer's conduct before deciding.
How do I check if my off plan handover is delayed?
To check whether an off-plan handover is delayed, open the Dubai REST app, choose Project Status (Mashrooi) and search for the project. Compare its projected completion date and completion percentage with the anticipated completion date and extension clause in your SPA. Save dated screenshots each time you check.
Can I stop paying if construction is delayed by the developer?
Stopping payments because construction is delayed can let the developer start termination under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020. Depending on overall project completion, up to 25% or 40% of the unit value can be kept. Get written legal advice before withholding any installment.
Can I get an independent view of how far the building has progressed?
An independent completion report on a Dubai off-plan unit is available from RERA's technical auditor for AED 15,000 per unit or villa, according to the DLD's FAQ. Before paying a developer's request, a buyer can also ask for a letter from the DLD-approved project consultant confirming the completion percentage.

Sources

  1. Project Status (Mashrooi) service guide, Dubai REST (Dubai Land Department)
  2. Frequently asked questions (Dubai Land Department)
  3. Track an under-construction property on your phone (Gulf News, 2023)
  4. Off-plan construction delays: options for resolution in Dubai (Afridi & Angell)
  5. Off-plan property disputes in Dubai: buyers' rights when developers default (HAS Law Firm via Mondaq)
  6. Law No. 19 of 2020 amending Law No. 13 of 2008 (Dubai Legislation Portal)
HomeProof Research TeamFacts from Dubai law and official registries. HomeProof sells no property and takes no commission. About HomeProof

This guide is general information, not legal advice. Laws and procedures change; check the official source before acting. Published 12 October 2026, last updated 12 October 2026.

Already bought off-plan?

Know where your project stands before every payment.

Track your off-plan instalments, and run a Property Check whenever you want the project's registry facts. HomeProof shows facts; what you do with them is your decision.

  • Installment Plan for your payment schedule
  • Property Checks against government registries
  • No commission from developers or brokers
Check a project