Check construction progress on your Dubai off-plan project before each payment

Check construction progress off-plan in Dubai before payment: completion percentage, escrow account and dates in Dubai REST, in a routine of a few minutes.

By HomeProof Research TeamUpdated 7 min readDubai law · every fact with a source

Short answer

  • The DLD's Dubai REST app shows a registered project's completion percentage, status, escrow account details and inspection details under Project Status (Mashrooi).
  • The DLD FAQ says payments follow completion rates, and an investor can ask for a letter from the DLD-approved project consultant confirming the current percentage before paying.
  • In Dubai, off-plan buyer payments must go into the project's escrow account; the DLD has publicly urged buyers not to pay outside escrow.
  • RERA asks developers to update the expected completion date and completion rate, so compare each payment request with the latest figures.
  • An independent completion report from RERA's technical auditor costs AED 15,000 per unit or villa.

Check construction progress on your off-plan unit in Dubai before payment of every installment: the percentage complete, the escrow account the money should go to, and the latest projected date. The routine takes minutes, and it uses official data rather than the developer's newsletter.

This guide sets out the routine, explains each data point and covers what to do when a payment request and the registry figures do not line up. It applies to Dubai only.

Key terms: Dubai REST is the Dubai Land Department's (DLD) official app. Mashrooi is its Project Status service. An escrow account is a bank account opened in the project's name to hold buyer payments. RERA is the DLD's regulatory arm.

How do you check construction progress off-plan in Dubai before payment?

Look up the project in Dubai REST, compare the completion percentage with your SPA's payment trigger, confirm the escrow account, and only then pay. The DLD website offers the same status lookup by plot number, project number or project name.

  1. Open Project Status (Mashrooi)

    In the Dubai REST app, open Services, choose Project Status (Mashrooi) and search by project name. Foreign investors log in with UAE PASS or a title deed, per the app's version notes.
  2. Read the completion percentage

    Note the percentage, the status label and the last inspection date. Take a dated screenshot.
  3. Compare with the payment request

    Read the installment trigger in your SPA. If it is linked to a construction stage, check whether the official figures support the request.
  4. Confirm the escrow account

    Match the account number on the payment request against the escrow account details shown in the app.
  5. Pay and keep proof

    Pay only into the escrow account. Keep the bank confirmation with the screenshot from the same day.

Dubai REST project status: reading the completion percentage

Dubai REST shows the official status of a registered project, including how far it has progressed. The DLD guide to Mashrooi lists project details and status, developer details, escrow account details and inspection details.

Completion percentage
In Dubai REST
Source: DLD
Status labels
Active / finished / cancelled
Source: Gulf News 2023
Escrow account number
In Dubai REST
Source: DLD
Independent audit
AED 15,000
Per unit or villa
Source: DLD FAQ

Gulf News (August 2023) adds that the app shows the construction start date, projected completion date, last inspection date, a downloadable inspection report, site photos and the project registration date. Read the percentage together with the inspection date: a figure from an old inspection says less about today.

Should I pay the next installment on my off-plan unit?

That decision is yours and depends on your SPA, but check the facts first. The DLD FAQ says payments follow completion rates and that, before paying a developer's request, an investor can ask for a letter from the DLD-approved project consultant confirming the current completion percentage.

Payment plans are set by the SPA. Some installments are tied to dates, others to construction stages. Know which kind your next payment is before comparing it with the registry.

…stop paying the installment because the developer has stopped building?
a buyer who had paid 60 per cent, writing to Gulf News' Ask the Law · Gulf News, Oct 2023

Stopping payments has consequences. Under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, a missed payment can lead to a DLD notice, a 30-day window and then termination, with the developer keeping up to 25% or 40% of the unit value depending on the whole project's completion. Read what happens after a missed off-plan payment and take legal advice before withholding anything.

Off-plan milestone payment check: what to compare

A milestone check lines up three things: what the SPA says triggers the payment, what the registry shows, and where the money is going. Mismatches in any of the three are worth a written question before paying.

Before-payment comparison
ItemWhere to find itWhat to compare it with
Payment triggerYour SPA payment planThe developer's payment request
Completion percentageDubai REST, Project Status (Mashrooi)The stage named in the SPA trigger
Escrow account numberDubai REST escrow account detailsThe account on the payment request
Projected completion dateDubai RESTThe SPA anticipated completion date
Last inspection dateDubai RESTToday's date
Investors must verify that off-plan projects are licensed and registered with an escrow account
Ali Abdullah Al Ali, Director of the Real Estate Control Department at RERA, Dubai Land Department · Gulf News, Jun 2024

Why does the escrow account matter at every payment?

In Dubai, off-plan buyer payments must go into the project's escrow account under Law No. 8 of 2007. In June 2024 the director of RERA's Real Estate Control Department urged investors not to make any payments outside the escrow account.

The escrow account is opened in the project's name and used only for that project, and its deposits cannot be seized by the developer's creditors (Article 9(1)). The DLD FAQ says withdrawals are generally limited to contractors, consultants and marketing, with marketing capped at 5% of total sales.

Escrow protects how your money is used; it does not guarantee that the project will be finished. Our guide to verifying the escrow account explains the check in detail.

What if progress looks stalled?

If the percentage has not moved across several inspections, act in writing. The DLD FAQ notes that where a project's completion does not exceed 5%, RERA monitors it, gives the developer time to correct, and starts cancellation if it does not.

When progress looks flat

If the projected date has moved, see what to do when the handover date changes, and for a wider delay, what to do when an off-plan project is delayed. Before your next transfer, check the project's official status and keep the record.

Buying from the UK, US, Canada or Australia?

Where can I see the completion percentage of a Dubai off-plan project?
The completion percentage of a registered Dubai off-plan project appears in the DLD's Dubai REST app under Services, then Project Status (Mashrooi), searched by project name. The DLD website also offers a project status lookup by plot number, project number or project name. Both show the project's status and inspection details.
Can I ask for proof of progress before paying an off-plan installment?
A Dubai off-plan buyer can ask for proof of progress before paying. The DLD FAQ says that before paying a developer's request, an investor can ask for a letter from the DLD-approved project consultant confirming the current completion percentage. Compare that letter with the payment trigger in the SPA.
Should I pay the next installment if construction looks slow?
Whether to pay the next off-plan installment is the buyer's decision, guided by the SPA. Withholding a payment can trigger the Article 11 default process, with a DLD notice and 30 days before termination. Check the registry figures, ask questions in writing and take legal advice before deciding not to pay.
How do I check that I am paying into the escrow account?
To check an off-plan payment is going into escrow in Dubai, compare the account number on the developer's payment request with the escrow account details shown for the project in the Dubai REST app. The DLD has urged buyers not to pay outside the project's escrow account. Keep the bank confirmation.
How much does an independent construction progress report cost in Dubai?
An independent completion report from RERA's technical auditor costs AED 15,000 per unit or villa, according to the DLD FAQ. The report gives a buyer an official figure for the project's completion that does not depend on the developer's own updates, which can help before a large installment.

Sources

  1. Dubai REST (Dubai Land Department)
  2. Project Status (Mashrooi) service guide (Dubai Land Department)
  3. Frequently asked questions on projects and payments (Dubai Land Department)
  4. Frequently asked questions (Dubai Land Department)
  5. Track an under-construction property on your phone (Gulf News, 2023)
  6. Dubai Land Department fines three developers AED 1.5m (Gulf News, 2024)
HomeProof Research TeamFacts from Dubai law and official registries. HomeProof sells no property and takes no commission. About HomeProof

This guide is general information, not legal advice. Laws and procedures change; check the official source before acting. Published 12 October 2026, last updated 12 October 2026.

Already bought off-plan?

Know where your project stands before every payment.

Track your off-plan instalments, and run a Property Check whenever you want the project's registry facts. HomeProof shows facts; what you do with them is your decision.