Short answer
- To check construction progress on off-plan Dubai property before payment, US buyers can open the project in the Dubai REST app's Project Status (Mashrooi) service, which the DLD says shows the completion percentage, site photos and the escrow account number.
- The DLD FAQ says payments follow completion rates, and an investor can ask for a letter from the DLD-approved project consultant confirming current completion before paying.
- An independent completion report from RERA's technical auditor costs AED 15,000 per unit, about $4,084.
Treat each installment request as a checkpoint.
How to check construction progress off-plan in Dubai before payment, for US buyers
Open the project in Dubai REST, compare the completion percentage with the milestone in your payment plan, confirm the escrow account number, and only then wire.
Read the payment request
Note the milestone it cites.Open Project Status
Completion %, dates, photos.Compare with the SPA
Does the milestone match?Ask for proof if needed
Consultant letter or auditor report.Wire to escrow only
Confirm the account number first.
Step 1: Read what the payment request is tied to
Your SPA (sale and purchase agreement) sets the payment plan; some installments follow dates, others milestones. Note which milestone this request relies on.
Step 2: Check the Dubai REST project status and completion percentage from the US
The DLD's Dubai REST page says off-plan investors can see project details including the completion percentage, actual project photos and the escrow account number. The DLD's guide to Project Status (Mashrooi) adds developer details and inspection details.
Gulf News reported in 2023 that the app also shows the projected completion date, the last inspection date with a report, and whether the project is active, finished or canceled.
Step 3: Compare the figures with your contract
If the request says a milestone is reached, the completion percentage should support it. The DLD FAQ says payments follow completion rates. Payment plans are set by each SPA, so read your own clause.
…stop paying the installment because the developer has stopped building?
Completion also matters if you stop paying. Under Article 11 of Law No. 13 of 2008, as amended by Law No. 19 of 2020, the share a Dubai developer may keep after a buyer default depends on the whole project's completion.
Most a Dubai developer may keep after buyer default, by whole-project completion
Values in % of unit value
If construction has not started for reasons outside the developer's control, or RERA cancels the project, the same article requires a full refund. If the numbers and the request disagree, see our dispute route map.
Step 4: Ask for written proof when the numbers do not match
The DLD FAQ says an investor can ask for a letter from the DLD-approved project consultant confirming the current completion percentage before paying a developer's request. For a fully independent figure, RERA's technical auditor will produce a completion report for AED 15,000 per unit, about $4,084 at the AED 3.6725 peg.
Check the date on the figure you are shown. The DLD FAQ says RERA periodically asks developers to update the completion rate and expected completion date, and charges a technical report fee where the report is more than three months old.
Step 5: Wire only to the project escrow account
The DLD FAQ says all amounts received from off-plan buyers go into the project escrow account. Confirm the number in Dubai REST against the invoice; our escrow verification playbook explains how.
Plan the timing. Dubai is 8 hours ahead of New York and 11 ahead of Los Angeles until November 1, 2026, then 9 and 12, so ask your questions in the evening and wire after the reply. If money already went elsewhere, read paid outside escrow. For the wider picture, see the global guide to construction checks and the overview for American buyers, or check the project's registry facts now.
Before the next installment: questions from American buyers
Should I pay the next installment on my off-plan property, as an American buyer?
Can I see the Dubai REST project status and completion percentage from the US?
How much does an independent completion report cost in Dubai?
Can my US bank reverse an installment wired to Dubai?
Related guides
- GuideCheck construction progress on your Dubai off-plan project before each payment
- Country hubDubai off-plan problems for US buyers: what can go wrong, from first deposit to dispute
- US guideVerify the escrow account for off-plan Dubai property: a playbook for American buyers
- US guideOff-plan dispute with a developer in Dubai: a route map for US investors
- US guidePaid the developer, not the escrow account, in Dubai: what to do now from the US