Short answer

  • Snagging, meaning a documented inspection for defects, is not legally required in Dubai but is widely recommended; get defects acknowledged in writing before you sign acceptance.
  • The DLD says extra area is not charged unless your contract says so, and developers must compensate for shortfalls beyond 5%.
  • After the completion certificate, the escrow agent holds back 5% of the project account for one year after units are registered to buyers; the DLD calls it a guarantee for defect repairs (Law No. 8 of 2007, Article 14).
  • The title deed is issued after the developer registers the completed project and your unit is fully paid; the DLD lists a title deed certificate fee of AED 250 for completed units.
  • Check the building's RERA-approved service charge in the Service Charge Index before accepting the keys.

What to check before handover in Dubai comes down to four things: the unit's condition, its measured area, the money held back for defects and the paperwork that makes it legally yours. Each has a rule or a documented practice behind it.

This guide walks through each check with its source, in the order you will meet them. It covers Dubai rules only.

A few terms first. Handover is when the developer gives you the keys and you accept the unit. Snagging is a room-by-room inspection that lists defects. The completion certificate marks the building as finished. The title deed is the final ownership document issued by the Dubai Land Department (DLD).

What to check before handover in Dubai: the four areas

A full handover check covers condition, area, the escrow retention and title. The table shows what each one depends on.

The four handover checks and their basis
CheckWhat to look forBasis
Condition (snagging)Defects listed and acknowledged in writingRecommended practice; not legally mandatory
AreaMeasured area against the SPA areaDLD FAQ: shortfall beyond 5% compensated
5% retentionMoney held for defect repairs for a yearLaw No. 8 of 2007, Article 14
Title deedProject registered and unit fully paidLaw No. 13 of 2008, Article 8; DLD FAQ

Snagging before handover in Dubai: why do it?

Snagging is not legally mandatory in Dubai, but it is the main way to put defects on record before you accept the unit. Property Finder's handover guide advises not to sign acceptance until defects are acknowledged in writing.

Snagging walk-through

Buyers abroad often use a representative or an inspection company for the walk-through. If you do, ask for a dated, photographed report addressed to you.

Area difference at handover in Dubai: what happens?

Measured area can differ from the area in your SPA, and the DLD sets out how each direction is treated. Extra area is not charged unless your contract allows it, and a shortfall beyond 5% must be compensated.

Extra area
Not charged
Unless the contract says so
Source: DLD FAQ
Shortfall threshold
Beyond 5%
Developer must compensate
Source: DLD FAQ
Escrow retention
5%
Held 1 year after units are registered
Source: Law 8/2007, Art. 14
Title deed certificate
AED 250
DLD fee for completed units
Source: DLD

Example: a unit sold as 1,000 sq ft that measures 940 sq ft is 6% smaller. Under the DLD FAQ wording, a shortfall beyond 5% must be compensated by the developer. A unit measuring 980 sq ft, 2% smaller, falls within that 5% band.

Ask for the final measured area in writing and compare it with your SPA before signing the handover documents. Read your SPA's area clause too, since the extra-area rule depends on what the contract says.

What is the 5% retention and how does it relate to defects?

The 5% retention is money kept back from the developer after the building is finished. Under Article 14 of Law No. 8 of 2007, once the completion certificate is issued, the escrow agent keeps 5% of the project escrow account's total value.

That amount is released to the developer one year after the units are registered in the buyers' names. The DLD FAQ describes it as a guarantee for repairing defects.

How does the title deed get issued after handover?

The title deed comes after two conditions are met. The DLD FAQ says a completed property moves to the Real Estate Registry, and the title deed is issued, after the developer registers the completed project and the unit is fully paid.

  1. Completion certificate issued

    The project is certified as complete. Article 14 of Law No. 8 of 2007 links the escrow retention to this moment.
  2. Developer registers the completed project

    Under Article 8 of Law No. 13 of 2008, developers must enter completed projects in the Property Register once they receive the completion certificate.
  3. You pay the balance

    The DLD issues the title deed only once the unit is fully paid.
  4. Title deed issued

    Your unit moves from the interim register to the Real Estate Registry. The DLD lists a title deed certificate fee of AED 250 for completed units.
…but until this moment, I did not receive the property…
a buyer who paid in full, writing to Gulf News' Ask the Law · Gulf News, Feb 2023

The 4% DLD registration fee is not a handover cost. It is charged at the off-plan registration stage, typically when the SPA is signed, according to the DLD and Gulf News.

Handover checklist for Dubai off-plan: the full list

The checklist below combines all four areas with the service charge check. Work through it before signing the handover acceptance.

Handover checklist, Dubai off-plan

Service charges become a regular bill once you own the unit, so look them up early. Our guide to the RERA Service Charge Index shows how to look up the approved rate, and service charge higher than expected explains what you can challenge.

If handover is later than your contract date, see what to do when the handover date changes. Before accepting the keys, check the project and developer facts in one place.

Buying from the UK, US, Canada or Australia?

Is snagging before handover in Dubai required by law?
Snagging before handover in Dubai is not a legal requirement, but it is widely recommended. A snagging inspection lists defects room by room so they are on record before you accept the unit. Property Finder advises not to sign handover acceptance until the developer has acknowledged the defects in writing.
What happens if my Dubai apartment is smaller than in the SPA?
If a Dubai off-plan unit measures smaller than the area in the SPA, the DLD FAQ says the developer must compensate for a shortfall beyond 5%. Extra area is not charged unless the contract allows it. Ask for the final measured area in writing and compare it with the SPA before signing.
What is the 5% retention at handover in Dubai?
The 5% retention is part of the project's escrow account that the escrow agent keeps after the completion certificate is issued, under Article 14 of Law No. 8 of 2007. It is released to the developer one year after units are registered in buyers' names. The DLD describes it as a guarantee for repairing defects.
When will I get my title deed after handover in Dubai?
A Dubai title deed is issued after the developer registers the completed project in the Property Register and the unit is fully paid, according to the DLD FAQ. Article 8 of Law No. 13 of 2008 requires developers to register completed projects once they receive the completion certificate. The DLD lists a AED 250 certificate fee.

Sources

  1. Law No. 8 of 2007 Concerning Escrow Accounts for Real Estate Development (Dubai Legislation Portal)
  2. Law No. 13 of 2008 Regulating the Interim Real Property Register (Dubai Legislation Portal)
  3. Frequently asked questions (Dubai Land Department)
  4. Request for sale registration (Dubai Land Department)
  5. Buying an off-plan property in Dubai: everything you need to know (Gulf News, 2026)
  6. House handover guide (Property Finder)
HomeProof Research TeamFacts from Dubai law and official registries. HomeProof sells no property and takes no commission. About HomeProof

This guide is general information, not legal advice. Laws and procedures change; check the official source before acting. Published 12 October 2026, last updated 12 October 2026.

Second opinion, before or after you buy

A check takes minutes. Not checking can cost everything.

HomeProof checks a UAE project and its developer against up to 80 parameters from government registries and open sources. We sell no property and take no commission, so you see the facts and make the call yourself.

  • Registration, escrow and completion data in one place
  • Developer delivery track record from open data
  • No broker, no commission, no verdict